Balcony: stages and schedule

Base, columns, covering and flooring. 7 stages over ~7 weeks, in the order they happen — some run in parallel.

Schedule

  1. 1. Base and foundation
    week 1 · 7 days ☂ Weather-sensitive
  2. 2. Columns and beams
    weeks 2–3 · 10 days ☂ Weather-sensitive
  3. 3. Covering
    weeks 3–4 · 10 days ☂ Weather-sensitive
  4. 4. Electrical and lighting
    weeks 3–4 · 5 days
  5. 5. Flooring and tiling
    weeks 4–5 · 8 days
  6. 6. Painting
    week 6 · 7 days ☂ Weather-sensitive
  7. 7. Finishes
    week 7 · 4 days

☂ Stages marked as weather-sensitive usually slip in bad weather — leave them some slack in the schedule.