Balcony: stages and schedule
Base, columns, covering and flooring. 7 stages over ~7 weeks, in the order they happen — some run in parallel.
Schedule
-
1. Base and foundationweek 1 · 7 days ☂ Weather-sensitive
-
2. Columns and beamsweeks 2–3 · 10 days ☂ Weather-sensitive
-
3. Coveringweeks 3–4 · 10 days ☂ Weather-sensitive
-
4. Electrical and lightingweeks 3–4 · 5 days
-
5. Flooring and tilingweeks 4–5 · 8 days
-
6. Paintingweek 6 · 7 days ☂ Weather-sensitive
-
7. Finishesweek 7 · 4 days
☂ Stages marked as weather-sensitive usually slip in bad weather — leave them some slack in the schedule.