Kitchen renovation: stages and schedule

Installations, flooring, cabinets and countertop. 8 stages over ~6 weeks, in the order they happen — some run in parallel.

Schedule

  1. 1. Demolition and removal
    week 1 · 5 days
  2. 2. Electrical and plumbing
    weeks 1–2 · 7 days
  3. 3. Plastering
    weeks 2–3 · 5 days
  4. 4. Flooring and tiling
    weeks 3–4 · 10 days
  5. 5. Cabinets and joinery
    weeks 4–6 · 10 days
  6. 6. Countertop and sink
    weeks 5–6 · 5 days
  7. 7. Fixtures and appliances
    week 6 · 4 days
  8. 8. Final cleanup
    week 7 · 2 days

How to use this template

In the Minha Obra app, when you create your project, pick "Kitchen renovation": the stages come with their dates, fitted to the start and end you set. You untick what you won't do, change names and dates, add stages and enter each one's amount — then follow expenses, pauses and delays.