Kitchen renovation: stages and schedule
Installations, flooring, cabinets and countertop. 8 stages over ~6 weeks, in the order they happen — some run in parallel.
Schedule
-
1. Demolition and removalweek 1 · 5 days
-
2. Electrical and plumbingweeks 1–2 · 7 days
-
3. Plasteringweeks 2–3 · 5 days
-
4. Flooring and tilingweeks 3–4 · 10 days
-
5. Cabinets and joineryweeks 4–6 · 10 days
-
6. Countertop and sinkweeks 5–6 · 5 days
-
7. Fixtures and appliancesweek 6 · 4 days
-
8. Final cleanupweek 7 · 2 days