Barbecue and outdoor kitchen: stages and schedule
Grill masonry, countertop and chimney. 7 stages over ~6 weeks, in the order they happen — some run in parallel.
Schedule
-
1. Base and foundationweek 1 · 5 days ☂ Weather-sensitive
-
2. Grill masonryweeks 1–3 · 10 days ☂ Weather-sensitive
-
3. Countertop and sinkweeks 3–4 · 7 days
-
4. Electrical and lightingweek 3 · 5 days
-
5. Tilingweeks 4–5 · 8 days
-
6. Chimney and hoodweek 5 · 4 days ☂ Weather-sensitive
-
7. Finishesweeks 5–6 · 5 days
☂ Stages marked as weather-sensitive usually slip in bad weather — leave them some slack in the schedule.