House or apartment renovation: stages and schedule

From demolition to painting and finishes. 8 stages over ~2 months, in the order they happen — some run in parallel.

Schedule

  1. 1. Demolition and removal
    week 1 · 7 days
  2. 2. Electrical and plumbing
    weeks 2–3 · 14 days
  3. 3. Plastering
    weeks 3–4 · 10 days
  4. 4. Flooring and tiling
    weeks 5–7 · 18 days
  5. 5. Drywall and ceiling
    weeks 6–8 · 10 days
  6. 6. Painting
    weeks 8–10 · 14 days
  7. 7. Fixtures and finishes
    weeks 9–10 · 8 days
  8. 8. Final cleanup
    week 11 · 3 days

How to use this template

In the Minha Obra app, when you create your project, pick "House or apartment renovation": the stages come with their dates, fitted to the start and end you set. You untick what you won't do, change names and dates, add stages and enter each one's amount — then follow expenses, pauses and delays.