House or apartment renovation: stages and schedule
From demolition to painting and finishes. 8 stages over ~2 months, in the order they happen — some run in parallel.
Schedule
-
1. Demolition and removalweek 1 · 7 days
-
2. Electrical and plumbingweeks 2–3 · 14 days
-
3. Plasteringweeks 3–4 · 10 days
-
4. Flooring and tilingweeks 5–7 · 18 days
-
5. Drywall and ceilingweeks 6–8 · 10 days
-
6. Paintingweeks 8–10 · 14 days
-
7. Fixtures and finishesweeks 9–10 · 8 days
-
8. Final cleanupweek 11 · 3 days