Bathroom renovation: stages and schedule
Plumbing, waterproofing, tiling and fixtures. 7 stages over ~4 weeks, in the order they happen — some run in parallel.
Schedule
-
1. Demolition and removalweek 1 · 4 days
-
2. Electrical and plumbingweeks 1–2 · 5 days
-
3. Waterproofingweek 2 · 4 days
-
4. Tilingweeks 2–3 · 8 days
-
5. Fixtures and finishesweek 4 · 4 days
-
6. Shower enclosure and accessoriesweek 4 · 3 days
-
7. Final cleanupweek 5 · 2 days
How to use this template
In the Minha Obra app, when you create your project, pick "Bathroom renovation": the stages come with their dates, fitted to the start and end you set. You untick what you won't do, change names and dates, add stages and enter each one's amount — then follow expenses, pauses and delays.