Bathroom renovation: stages and schedule

Plumbing, waterproofing, tiling and fixtures. 7 stages over ~4 weeks, in the order they happen — some run in parallel.

Schedule

  1. 1. Demolition and removal
    week 1 · 4 days
  2. 2. Electrical and plumbing
    weeks 1–2 · 5 days
  3. 3. Waterproofing
    week 2 · 4 days
  4. 4. Tiling
    weeks 2–3 · 8 days
  5. 5. Fixtures and finishes
    week 4 · 4 days
  6. 6. Shower enclosure and accessories
    week 4 · 3 days
  7. 7. Final cleanup
    week 5 · 2 days

How to use this template

In the Minha Obra app, when you create your project, pick "Bathroom renovation": the stages come with their dates, fitted to the start and end you set. You untick what you won't do, change names and dates, add stages and enter each one's amount — then follow expenses, pauses and delays.