Building from scratch: stages and schedule

A one-storey house, from clearing the lot to handover. 15 stages over ~9 months, in the order they happen — some run in parallel.

Schedule

  1. 1. Site preparation
    weeks 1–2 · 10 days ☂ Weather-sensitive
  2. 2. Foundation
    weeks 2–6 · 30 days ☂ Weather-sensitive
  3. 3. Structure
    weeks 6–12 · 40 days ☂ Weather-sensitive
  4. 4. Masonry
    weeks 9–15 · 45 days ☂ Weather-sensitive
  5. 5. Slab
    weeks 15–18 · 20 days ☂ Weather-sensitive
  6. 6. Roof
    weeks 18–21 · 25 days ☂ Weather-sensitive
  7. 7. Electrical
    weeks 16–22 · 40 days
  8. 8. Plumbing
    weeks 16–22 · 40 days
  9. 9. Plastering
    weeks 22–26 · 30 days ☂ Weather-sensitive
  10. 10. Subfloor
    weeks 25–27 · 15 days
  11. 11. Flooring and tiling
    weeks 27–32 · 35 days
  12. 12. Doors and windows
    weeks 31–33 · 15 days
  13. 13. Painting
    weeks 32–36 · 30 days ☂ Weather-sensitive
  14. 14. Fixtures and finishes
    weeks 36–38 · 15 days
  15. 15. Final cleanup
    weeks 38–39 · 7 days

☂ Stages marked as weather-sensitive usually slip in bad weather — leave them some slack in the schedule.