Barbecue and outdoor kitchen: stages and schedule

Grill masonry, countertop and chimney. 7 stages over ~6 weeks, in the order they happen — some run in parallel.

Schedule

  1. 1. Base and foundation
    week 1 · 5 days ☂ Weather-sensitive
  2. 2. Grill masonry
    weeks 1–3 · 10 days ☂ Weather-sensitive
  3. 3. Countertop and sink
    weeks 3–4 · 7 days
  4. 4. Electrical and lighting
    week 3 · 5 days
  5. 5. Tiling
    weeks 4–5 · 8 days
  6. 6. Chimney and hood
    week 5 · 4 days ☂ Weather-sensitive
  7. 7. Finishes
    weeks 5–6 · 5 days

☂ Stages marked as weather-sensitive usually slip in bad weather — leave them some slack in the schedule.